Accidentally close the Sprint without selecting Done on some tickets, is there a way to move them to an earlier closed Sprint?
Appreciate if anyone could assist, thank you.
Hi @James Lim ,
If you can see the Sprint id on the Issues screen, you can directly associate with the closed sprint. If you can’t see this field try to use bulk change to change the sprint id.
Hi @Ollie Guan ,
Thanks for your swift help, I tried looking into the options, but don't think I could move tickets to a previous closed Sprint.
I closed Sprint 2 and brought forward remaining tickets to Sprint 3, then I realised some tickets (with subtask) should be "Done" in Sprint 2, now how do I move them from current Sprint 3 back to closed Sprint 2?
Thank you.
You have to re-open the sprint in "Reports" section. Move this desired ticket to the reopened sprint, mark it as done and complete the sprint.
I have the same issue
@Ollie Guan it only give me the option to move the ticked up and down the swim lane on done swim lane on the same open sprint . It won't let me move it back to previous sprint . I have two parallel sprint open now
If I have moved it to done on the new sprint and now i want to move to previous sprint how can i do that ? Desired sprint i want to move it to was closed . I reopened it and now i have to active sprints in parallel
It looks like you're new here. Sign in or register to get started.