Here is the scenario
- I created an Initiative.
- Created two epics with Initiative
- Created two stories with one of the epic
- Assigned a release with a fixed release date (31-July-18)
- Gave story points to Initiative only
- Clicked 'Calculate'
- As a result, Timeline showed that initiative will be done by 10-July but stories within that will be completed by 31-July.
Is it not an incorrect representation? This indicates that there is no relationship between Initiative and Story.