I'm working in a JIRA cloud instance and testing out Portfolio for JIRA. It says that the estimation fields are required for it to work. I do not seem to have the Original Estimate or Remaining Estimate fields in my JIRA instance. Is there a way to get those back? Or is there a way to map custom estimate fields to Portfolio?
Thanks!
Hello @Heather Stoddard
Please make sure you have time tracking enabled on the cloud instance
https://confluence.atlassian.com/adminjiracloud/configuring-time-tracking-818578858.html
And also add the "Time tracking" field to the screens of the issueTypes -> projects.
See here
https://community.atlassian.com/t5/Jira-questions/The-Original-Estimate-field-is-missing-when-creating-stories-and/qaq-p/95261
The Time Tracking was active. I granted permissions to application access: Jira software. I went back and tried to add the fields to my issue screens, but it's still not available as a choice.
The field which you have to add is called "Time tracking"
Thank you! This did it! Now I just have to figure out how to make the User Story time tracking will have an effect on the Epic Remaining Time.