If I enter 8h for a task estimate it converts and displays as 1d 1h (because available hrs is 7). I just want it always to show hours - 8h.
Thx
Rick
Hi Rick,
From the JIRA Admin cog-> Issues-> Issue Features > Time Tracking, you can change the time display format, as shown in this picture:
Hope it works,
Carlos
Carlos,
Thx for the reply. Yes that was exactly what I was looking for. Might clarify though that you have to Deactivate the Time Tracking in order to see the screen you presented. Once I figured that out worked like a champ.
I'm glad it worked!