I am a creative services project manager that works at a tech company. I interface directly with Business Units (BU) on their marketing requests and then take those requests to our internal graphic designers/design team to implement.
Besides creating a checklist, is there a way to add a pre-set schedule within a card?
See example of what we are trying to achieve below.
11/7 - Content recieved by Project Manager
11/9 - Content edited by Copywriter
11/10 - BU approved copy. Copy ready for layout.
11/14 - BU review copy/design layout
11/15- Design team makes edits
11/17 - BU conducts final review.
11/19 - FINAL DELIVERABLE DUE