We are currently using JIRA Portfolio and have dependencies defined in JIRA as Requires and Required by. The configuration of Portfolio has this dependency type specified.
Within Portfolio, dependencies can be added to issues and you can see the dependencies in the scope timeline and also scheduling algorithms take dependencies into consideration.
The issue is within the Reports section of Portfolio. When I navigate to the Dependencies report, nothing shows up. It only says: "We couldn't find any dependencies in your plan, based on the time it was last calculated.Last calculation: 11/Oct/17 08:19 AM". This occurs regardless of the filter set for release, hierarchy level, date range, etc.
I have gone through everything I can think of to try to resolve this issue but am lost at this point as to what can be causing the report to not produce results. Any ideas on what might be the issue?