Hi,
Using Bamboo 5.9.2 with Subversion. Our deployment process runs a set of predefined tasks, some of these tasks cannot be rerun and any of the tasks could fail.
If task #5 fails, currently we need to edit the deployment plan and manually disable tasks 1-4 before rerunning and then remember to re-enable the tasks once deployment completes successfully.
Is it possible to configure Bamboo deployment process to automatically 'skip' tasks that were previously completed successfully when re-running a deployment/release (i.e. start with the first failed task)
I could imagine each task would contain an option to preserve its state, and when deploying an option would be to ignore already completed tasks (if task is configured for that)
Cheers,
Paul