I've built an automation rule in Jira Product Discovery that updates the "Target Delivery Quarter" field based on changes to the "Targeted Delivery Date" field. The Target Delivery Quarter is used as our column value for the board's roadmap view to visualize by quarter.
Current Setup:
- Automation calculates the quarter based on the Targeted Delivery Date
- Targeted Delivery Date is configured to auto-fill based on linked delivery work items' due dates (using JPD's auto-fill functionality)
- Goal: reduce multiple manual updates for PMs
- I used this community article to help build out my automation
Issue: The automation triggers successfully when the Targeted Delivery Date is manually updated, but it does not trigger when the Targeted Delivery Date is auto-filled after a linked work item's due date changes.
Question: Is this a known limitation with the "field value changed" trigger when the value updates through auto-fill rather than direct manual input? Are there any workarounds to make the automation respond to auto-filled field changes?
Any insights or alternative approaches would be appreciated!