Hi all.
A lot of my recent work is in hybrid environments so asks from an existing PMO.
The Jira plans work really well and very successful in moving dependency away from MS Project and other static tools.
My question is specifically around Scenario Planning in Plans. While you can create scenarios to discuss a work and timeline change, if you confirm a timeline change, the original timeline becomes lost.
PMOs often ask for current plan versus original, so wondering how people have accommodated this ask ? Is it just a matter of exporting the original and comparing or something else I may be missing ?
Thanks in advance.