Curious about actuals from JQL or Jira reports regarding average time to complete various story estimates. On average, how long did a story estimated at a "1" take us to deliver? How about at "2", a 3, 5, 8, 13....
Thank You
Hi @Matt Boon -- Welcome to the Atlassian Community!
You cannot answer a question like that with out-of-the-box JQL.
Instead you could use the built-in, Atlassian interpretation of a control chart, as described here: https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-control-chart/
With that, and some quick filters by story sizing, you may answer that question. This approach will also help you to see outliers from the normal measures.
Kind regards,Bill