Hello,
we try to switch with our continous integration to bamboo and got a problem with the plan dependencies.
We use one subversion repository that contains multiple projects. One of those is a project which contains a lot of external components that are shared by all the other projects. I set up a plan that is triggered every night and checks out the components and builds them first. After that it triggers all the plans building the other projects using the child-plan dependencies. That works!
But now we need the possibility to manually start a plan of a certain project and run the build-plan for the components !before! the product-plan itself starts (so only the components and the specific project-plan should start). I can't work with blocking dependencies, because they don't work for manually or scheduled triggers.
Is there an other way to realize this kind of dependencies with bamboo?
Thanks,
SMu