Hi All,
is there something possible to copy one plan variables to another plan variables when first plan execution gets completed. I want to use variable values of first plan to another plan
Thanks
Shahjad
Hello @shahjad ahemad
The default Bamboo setup does not provide that feature. Still, you can install the "Variables tasks for Bamboo" app and add a "Copy variable configuration" to your source plan, selecting scope as "Plan/Deployment Environment" and enabling "Include global variables".
Your "destination Plan" will have to load the desired variable globally.
Cheers,
Eduardo AlvarengaAtlassian Support APAC
--please don't forget to Accept the answer if the reply is helpful--
It looks like you're new here. Sign in or register to get started.