In Portfolio, what causes the error "Item ignored. The item is assigned to an invalid sprint."?
I am getting this error and am trying to debug, but I don't know constitutes as 'invalid'. Thanks!
Same Problem here. Issue is assigned to a sprint which is associated with the team.
Hey Anton,
Do you have parallel active sprints from Agile? That can also cause this error because one of the parallel sprints will be ignored by Portfolio.
yes, i do. But each Issue is only assigned to one of those two sprint.
The second Sprint is also from another project board.
Agile gives me the opportunity to show and work on mulitple amount of Sprints in the same Board. So why is thit a problem for portfolio?
Unfortunately we currently don't have support for Parallel sprints from the same board as this is quite tricky for Portfolio. Right now the sprint that is active parallel sprint ranked highest in the agile backlog is the "valid sprint".
We're currently developing a solution for this problem but we don't have a good answer yet. In the meantime we recommend creating separate boards for each stream of sprints. Please let me know if this doesn't work for your use case.
Also just a question regarding your use case, do you require to see both parallel sprints in your plan or would you be satisfied if you could pick one of the parallel sprints to use in your plan? (i.e this suggestion: JPO-1510)
We have the same issue. We have two teams who work out of the the same board as we often need to share tickets across tickets. We use parallel sprints so each team's sprint planning is easier. Unfortunately this means half of my combined teams work won't work in Portfolio.