Hi there,
I have multiple teams working in Jira and we have been trying to roll out the Advanced road maps to track progress and dependencies of the Deliveries. Needles to say it has not been easy and we still have a lot to do.
My issue with the Dependency view, is that currently even thought I try to Roll up to Epics I can still see all the Stories and Tasks and dependencies between them, but not a roll up view. We have also introduced an Initiative in the issue hiarchy to be above Epic, but no matter what Roll-up option I choose, the Stories are still there.
I checked that though part of plan, those particular Stories do not belong to any Epic - does it mean that first we need to get every single Story under an Epic, to get the roll-up function in the Dependency view to work?
Any help or explanation how to fix this is much appreciated 
With kind regards,
Vilhelmine