I am a new user of advanced roadmaps, and experimenting with auto-scheduling. I have a set of sub-tasks assigned to one person, and was hoping that auto-scheduling would move them to ensure that person is not overloaded (i.e. change the dates so they are sequential, rather than concurrent). However, when I run Auto-Schedule, the dates are unchanged.
I'm wondering whether this is something that auto-schedule should be able to do, and if so, what I need to do to achieve that?
Thanks,
Stephen