We are using Sprint Capacity view to manage the team and sprint.
Found the "Sprint Box" working days allocated are calculated by issues "Remaining Estimate". When sprint is close to the end , working days allocated will be lesser as issues are completing (have worklog and remaining estimate are reducing).
Below is a demo. I created an issue with 2w (10 days) original estimate. I input worklog 5 days. Remaining estimate become 5d (10 minus 5). The sprint box working days allocated will show 5 instead of the original estimate 10d. It looks weird to my team. As we thought the working days allocated should be always counting "Original Estimate".
If we change the view to use Story Point, worklog would not reduce the story point in sprint box
Anyone know the definition of "working days allocated" when using Days/Hours for display. Thank you.