we are testing the advanced roadmaps functionality in our projects before buying the premium version of Jira and there's a behaviour we don't understand, let me give you the details of the scenario:
- Using the Improverd interface,
- backlog of 50 items all of them estimated in story points
- 4 releases scheduled (with the consequent items assigned ont he fixVersion field)
- Velocity of the team defined (using Scrum and 2 weeks Sprint Length)
- Team members left empty for now
- 2 sprints actually created in the Sprint board with some assigned items (around 10 between the 2 of them, having some in Done status, some in Progress) , the remaining 40 items are in the product backlog without sprint assignment but Ranked following the releases order). No further sprints are yet created here.
- Dependencies configured as Concurrent
- Hierarchy at Story level
- View Settings: Group by Release and Sort by Rank
When clicking on Auto-schedule I'm getting reordered in the plan the none assigned sprint items and scheduled at some point in the timeline (that's the expected thing), but when I see when they have been scheduled I realise that in the calendar there are at least a couple of future autocalculated by "Plans" sprints which don't have any task assignment ¿? causing my plan to delay beyond what it should be, any idea?