Issue:
Portfolio tells me that I have 14 unestimated tickets in one sprint in the capacity view of a teams sprint. But I can not figure out, which tickets are unestimated. See first pic
Checks till now:
- I check that all tickets have story points
- In the scheduling option in portfolio, the story point filed is selected for estimation (See second pic)
- In the board option, the story point field is selected for estimation (see thrid pic)
Version:
we are currently using the following versions. An update is in planning.
- Jira 8.5.1
- Portfolio 3.21.0
----------------------------------------------------