Hi to all,
we use the Roadmap pluging for work planning for a kanban team.
It is possible to set the team capacity and then the "remaining effort" field for each story in the plan. The Roadmap plugin distributes the "remaining effort" over whole planned time period for a certain story.
Expected behavior:
* remaining effort is distributed over remaining time (today until due date)
Observed behavior
* remaining effort is distributed over whole planned time (start date until due date)
** This is valid for "original estimate", but it isn't valid for "remaining effort"
Requirements behind my expectation:
* We configured the plan to show the available/planed capacity of a team in timeline. If we make no progress on a certain story, i.e. "remaining effort" is not changed, we need to do the remaining effort in a shorter time period for each day which pass by and no progress was made (the due date is fixed). That's why we expect to have the remaining effort distributed along the remaining time only.
* We always want to have an updated view on future workload in our team
Questions:
* Is my expectation correct? If not, why?
* Is it possible to configure a roadmap plan to fit to my expectation?
* Is there another way, to fulfill requirements described above?
Thanks in advance and best regards,
Alessa