My JIRA Portfolio project has two stages: Design and Development. These stages correspond to an issue status workflow my team is following in Kanban style. The process goes something like this:
Design
- Flowchart
- Wireframe
- Mockup
- Design Review
Development
- To-do
- In Progress
- In Review
- Done
The Design stage is noted as complete when issues are moved into To-do, and the Development stage is noted as complete when issues are moved into Done.
When using Portfolio's stages, there doesn't appear to be any way to map my issue statuses to stages.
So, for example, when I recalculate my plan, tasks that have already been completed in the Design phase are moved "forward" in the plan as if they still need to be completed.
Ultimately my question is how does Portfolio understand that different stages of a task are complete?