Hi,
We're exploring jira portfolio now (in the past I evaluated portfolio1.0 and it wasn't enough for me)
I am trying to understand some things about capacity....
I manually put weekly hours for every team member in my shared team. interesting enough - when I go to my portfolio plan into teams I see that the teams have a default capacity of 200 hours, regardless of the number of team members or their weekly hours...
Am I missing something? is there a specific reason why the team will not, at least, set the default to the aggregated number of weekly hours of all members?