Hi,
I am doing my first test plan (improved interface):
- I have 3 epics x 2 issues each, all with 2d estimation.
- I have a team with 2 members each with 40 hours per week capacity equaling 5 days per week.
Portfolio squeezes all issues to just one day implementation, implicating (I guess) that both team members work together on all issues and thus are able to finish them off in just one day.
Is there any configuration magic to avoid this? Especially in software development it is completely unrealistic to put two developers on the same task.
Thanks and regards,
Anton