On Portfolio version 3.1 - new experience.
I do not understand how the "Target start" and the "Target end" fields are computed by the scheduler.
My configuration is:
- Kanban team with 40h weekly capacity
- One release planned for 03 July 2019
- One story (US1) with estimates of 10 days
- A second story (US2) with estimates of 30 days depending on the first one (US1).
After auto-schedule, the start date and end date are as follow:
- US1: 9 May -> 15 May (6 days)
- US2: 16 May -> 04 Jun (19 days)
I would have expected that the minimum would be the estimates with potentially the weekend added.
I would also assume that, due to the dependency, the minimum elapsed days would be 40 days whatever the team capacity is as the documentation states that there is only one assignee by issue.