Learned from a session at summit19. Task switching (multi-tasking) causes a task to require 40% more time.
We refer to that as "Context-Switching" in our group and it's indeed very dread-upon by any devs in our team.
When we plan the sprints with the team, we try to keep the task of the same type to the same person to avoid "context switching" as much as possible.
In our group, there's 2 types of "context switching" :
The unavoidable cannot be planned since it's caused by end-users interruptions, the way we handle those if by dedicating someone to end-users support in a sprint, meaning that we know that person is going to be less efficient, so we plan accordingly for him/her. For the avoidable one, it's the responsibility of both the employee and the sprint owner to make sure they handle that properly.