I am evaluating JIRA portfolio and find a number of bugs. We use cloud version.
- When a plan is created by adding only epics AND excluding all JIRAs without epics, any new JIRA gets automatically added to the plan. Even when that new JIRA is not part of any included epics. This is super frustrating. We would need to manually exclude those JIRAs from the plan.
- Portfolio view limits the number of fields it shows. We can't make it to display "forecasted completion date" (custom field added for all epics in our installation) for example.
- Portfolio embedded view (to embed in the confluence) has its own limitations. It shows story points, progress, target due date. That's all. If I want to remove story points or add assignee to embedded view, there is no way to do that.
- If the entire plan is going to take another 9 months to complete, we can't see full view of schedule for next 9 months. The schedule view stops after 2 months.
- The way the tool shows progress is incorrect. I have an epic which has more than 60% completed. But, portfolio view shows only 20% completed.
Does anyone face the same problem? If yes, how did you resolve it? Any help is appreciated.