The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Automation - using # of items in list as trigger for movement in/out

Steve West
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 14, 2023

Hi all- looking to use automation to drive my workflow a little bit better.

I have three lists:

  • Backlog
  • In Process
  • Done

I only want to have three items in the list at one time, so I've been using the trigger "when list has fewer than 3 items" as a starting point. Once I move an item from In Process to Done, I'd like the automation to move the top card from the Backlog list into the In Process list. But I can't seem to find the Action that would do that.

 

Is this something that is possible with Automations? Thanks!

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Mike - Dreamsuite Consulting
Community Champion
August 15, 2023

You can indeed to this...

Screenshot 2023-08-15 094523.png

Steve West
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 15, 2023

Thanks Mike, this worked perfectly! Really appreciate the help.

Mike - Dreamsuite Consulting
Community Champion
August 15, 2023

No problem.  Using Trello as a pull system seems absolutely perfect to me....