While trying to aggregate multiple plans from differnt teams into one programm plan Jira uses a calculated end date and not the target date from the individual plans for each epic. some Initiatives/Epics out of the hierarchy aren't even shown in the aggregated plan. is there a fix to use only the target date for such a plan?
Yes, if you have target start and end, as I do. In the configuration screen you can choose those.
As an example, I have created a project to house all initiatives. I have a plan that pulls in all initiatives from that project and then displays them on the roadmap by target start and target end dates. Hope this helps
It looks like you're new here. Sign in or register to get started.