You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I started to use a BigPicture resently, and using the Gantt chart met a problem.
All Manuals says, that if I link tasks with strong dependencies, moving one task will affect the another, linked one.
But in my case it is not happening, BP only highlight the incorrect link without moving another.
Example:
Two tasks connected end-to-stark way.
I move first task forward
second task do not move, only link bocame orange.
How to turn on the auto reschedule?
Thank you in advance