how to add values in the dropdown of estimation ?

Nirmal Kumat January 17, 2024

Hello all - I need to know that when we go and configure a project board, then we see this estimation method dropdown.

How can we add values to this estimation method dropdown ? (i wanted to remaining time estimate but its not in dropdown right now)  see below snapshot for reference.. pls help on this.

 

image.png

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 17, 2024

Welcome to the Atlassian Community!

The estimates for a board can be run off the time estimates, or any other numeric field you have.

To add options into that list, add a numeric field to the project.

Remaining time is not a suitable number to do scrum estimation from because it changes as people log time.  A scrum estimate is supposed to be a fixed number when the sprint starts (hence original estimate is a good candidate)

Nirmal Kumat January 17, 2024

thanks for the help. can you guide me how to add numeric field to the project in order to add options to that list.

 

Also in the backlog view of the project we can either see story points or original time estimate for issues. Is there a way that we can have a view of both story points and original time estimate for the issues in backlog view.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 17, 2024

Story points is already a numeric field, but you can add your own.  In global admin, go to issues -> custom fields and add a new one, making sure you select "number" as the field type.  You may want to restrict it to the projects your board looks at.  You will need to add it to the screens for those projects as well.

The selection field for "Estimation method" only lets you select one field, and that then becomes the board's sprint estimate, which is the column you see in the right-hand side of your backlog.

Other fields named in there are just fields, they are not the sprint estimate.

You can get them shown in the backlog by configuring them as fields on the backlog rows - go to board config -> card layout.