Dear Team,
In our Redlight-AI Project created Stories, task, Subtask which are completed in assigned sprints after completing current sprint why it moves automatically to next sprint.
Welcome to the Atlassian Community!
This is most likely because you are not telling Jira that the issues are "done".
To be done, they have to be in the last column of their board, and not have any open sub-tasks.
Hi @Priya Mishra welcome to the community.
This happens when status is "Done" category, but the resolution field is empty.
Jira understand that the issue is completed, when resolution is set.
https://confluence.atlassian.com/cloudkb/best-practices-on-using-the-resolution-field-968660796.html
This is the kb related