The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

What happens to Story sub-tasks if the Story is moved to be a Sub-Task of another Story?

hitesh.rawal
May 6, 2020

I have a Story A which already has some sub-tasks. I need to move this to be sub-task of another Story B.   What happens to the sub-tasks of Story A if I move it?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
John Funk
Community Champion
May 6, 2020

Hi Hitesh - Welcome to the Atlassian Community!

Sub-tasks cannot have Sub-tasks under them. You would need to move the Sub-tasks under A to another parent before you move A as a Sub-task somewhere else.

hitesh.rawal
May 7, 2020

Thanks John