I create a sprint from 04/01/24-04/12/24 until the year, each sprint is two weeks.
I open an issue and I go to the details tab i don't see the sprints only future sprints.
THE FILTER ONLY SHOWS ME FUTURE DATES
Jira does not allow the feature of adding issues to sprints that have end dates in the past.
There are 3 backlogs:
Product backlog: all open issues issues
Version backlog: all unreleased issues for that version
Sprint backlog: unresolved issues in a sprint
The mindset is about planning for the future, not the past.