The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

What cant i see all my sprints when i try to add it to my issue

Ricardo Sanchez
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 1, 2024

I create a sprint from 04/01/24-04/12/24 until the year, each sprint is two weeks.

I open an issue and I go to the details tab i don't see the sprints only future sprints.

THE FILTER ONLY SHOWS ME FUTURE DATES

WHen i search.pngWHEN I OPEN SPRINT LABEL.png

 

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
LynnG
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 1, 2024

Jira does not allow the feature of adding issues to sprints that have end dates in the past.

There are 3 backlogs:

Product backlog: all open issues issues

Version backlog: all unreleased issues for that version

Sprint backlog: unresolved issues in a sprint

The mindset is about planning for the future, not the past.