Hi!
I have the existing plan where i have multiple EPICS and attached tasks/ User Stories.
When i add new Tasks to the JIRA Epic, i am unable to see them in my Plan view. Just to mention i have created New Tasks in JIRA and not through the plan view.
Please help why i am unable to see the newly added tasks of EPIC in plan view.
Hi Vikash,
I've added the portfolio tag to your question so it shows up in the right product category and could be easier found by others that might be able to help.
The first thing I think about is the fact that you could be using a Classic Plan and not a Live Plan. If that's the case there should be an "Update to date" button. See "Updating a plan" for more info.
Hope this helps.
Best,
Maarten