Time spent visible in Plans?

jeroen_wilmes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 18, 2024

Is there a way to present the Time Spent on issues in your Jira Plan (advanced Roadmaps) as a columns in "Fields"?

The only way I know, is to show the progress in days, and then by hovering over the progress bar you can see the Time Spent, but that is not the way that works for stakeholders. They simply want to see the number of days (hours) spent so far on an issue.

It does mean the data is there but it is not presentable which is frustrating.

1 answer

1 accepted

0 votes
Answer accepted
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 18, 2024

Hi again @jeroen_wilmes

Yes indeed - the idea behind advanced roadmaps is planning, not reporting on what has been done. Since it is a forward looking tool, completed issues also disappear from the plan after some time (default 30 days). There is also a limit of - if I am not mistaken - 5.000 issues at max in a plan, which may also become limitative after some time and for cross-project plans.

To report on work done towards stakeholders, it may be better to use other reporting features in Jira (or via reporting tools) better suited for the job.

Hope this helps!

jeroen_wilmes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 18, 2024

@Walter Buggenhout , thanks for explaining. I see your point. 