Hi,
in the roadmap view, only the epics do have time bars displayed with their respective start- and end date. All issues in the hierarchy directly under the epic do also have start and end dates but not a single time bar is displayed for these.
Does anyone know how to fix this?
Thanks a lot!
nevermind, fixed it, for anyone having the same issue: there is a setting in the project settings like "display time bars of subordinate tasks" that you need to toggle.
I have no idea why this isn't the default but anyway :D
While investigating, I assumed it might be that I accidentially created custom fields for start and end date (which explains why [cf000nnn] does appear many times as choosable options when creating dashboards) so I removed them and used the non-custom fields "start date" and "target end" but the time bars still do not appear.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.