I work in a marketing team and we are looking to implement Scrum as our agile method, as I was trying to build the roadmap, I've found that my task do not show the correct timeline.
What I'm seening is that every task I build just shows the purple bar as if the start and due date is the same as the sprint and not the real one selected which is usually between the sprint.
What should I do?
Hello @Jose Miguel Hurtado Escobar
Welcome to the Atlassian community.
By default the roadmap will show the tasks with dates matching the Sprint dates.
You can change the Roadmap configuration to use start and end dates from the issues themselves instead.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Glad to help.
If your problem has been resolved please consider mrrking the Answer as Accepted to help other users find posts with validated answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The tags on this post indicate the user is using the Jira Cloud product, so the answers are specific to Jira Cloud.
If you have a question about Jira Data Center, please start a new Question by clicking on the Ask a question option at the top of the community screen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.