Query issues with changed status in the last 2 days

Artūras Rimkus March 24, 2021

Following advice of some other answers in this forum - like this one - I tried writing a JQL query that would return all issues that have their status changed from TO DO to IN PROGRESS within the last 2 days, like so:

status changed FROM "To Do" TO "In Progress" AFTER "-2d"

However, I get no results, even though I am certain there are issues that would meet the query. What am I doing wrong?

1 answer

1 vote
Zoryana Bohutska _SaaSJet_
Atlassian Partner
March 24, 2021

Hi @Artūras Rimkus 

This JQL works for me.

Do you want only to show a list of issues or return to some status?

Artūras Rimkus March 24, 2021

Hi. I just need the list of issues. And the fact that it works for you is both reassuring and confusing... :)

Artūras Rimkus March 24, 2021
Zoryana Bohutska _SaaSJet_
Atlassian Partner
March 24, 2021

If you don't find another solution, you can try the Dynamic Filter app (developed by my team). It allows creating advanced filters for next-gen and classic projects. To filter the issue list by your request, do such steps:

1. Add Smart Field

2021-03-24_17-29-47.png

2021-03-24_17-16-34.png

2. Create a Dynamic filter by adding before created Smart Fields. And save it (optionally, you can save it for Jira filters).

2021-03-24_17-27-17.png

Hope, you will find the best solution for yourself. 

Suggest an answer

Log in or Sign up to answer