In classic Jira projects we are able to remove non-working days from a Sprint to help more accurately plan velocity. I've looked at the documentation for Next-Gen projects and this doesn't seem to be present. Am I missing it, or is this not implemented yet?

5 answers

1 accepted

5 votes
Answer accepted
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 19, 2018

Hi Mason,

Currently, next-gen project does not have "Board settings", so it's not possible to configure the Working days.
Based on your question, I've created a feature request:
- https://jira.atlassian.com/browse/JSWCLOUD-17331
Please, click on vote and watch to receive updates about the feature.

Regards,
Angélica

mason.fitch
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 19, 2018

Thank you Angelica.

Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 20, 2018

You are always Mason!
If you have any other question, please count on us.

Regards,
Angélica

Victor Burgos May 29, 2019

What the... why remove features from Next-Gen? Next-Gen should have the same, if not more) features from old Jira. 

marek.wituszynski
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 25, 2019

@Victor Burgos Next Gen is written from scratch - we can expect that more and more features will be added. Here's the roadmap that might be of help:

https://www.atlassian.com/roadmap/jira-software

Richard Kiefer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 9, 2020

Of course we can expect more and more features to be added, after losing some coming from classic. *face palm* sorry. That is just a very weak reply to respond to feature loss... especially for such elemental aspects like working days, where without this feature, burndown charts just become useless. And noone noticed that during rewriting from scratch? Again, sorry for my frank words, but that is a weak statement.

Like # people like this
Bogdan Barna
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 28, 2022

@Angélica Luz  any news about this?

On the ticket you've created there is this sub-task, marked as CLOSED https://jira.atlassian.com/browse/JSWCLOUD-17773

3 votes
Daniel Morris
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 15, 2020

Why has this question been resolved?

It's now been two years. Are you planning to implement this issue?

2 votes
jeremie
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 29, 2020

Hello, I was looking to hide weekend from my next-gen Roadmap today as well. 

2 votes
mvanlammeren
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 30, 2019

Actually, I think that JSWCLOUD-17666 better represents the original poster's request. The other "board settings" features from classic Jira are nice, but without non-working days, the burn-up report misrepresents the data presented.

https://jira.atlassian.com/browse/JSWCLOUD-17666

0 votes
Arthur Konrath
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 25, 2023

https://jira.atlassian.com/browse/JSWCLOUD-17666

4 years ago...

is it ever going to be done?

Suggest an answer

Log in or Sign up to answer