How would one create an initiative (level +2) as a parent link to an epic (level +1) in a field in Jira Software.

We have added the issues types and create the hierarchies but are unsure of how to link epics to initiatives via a custom field and what the field type would be.

1 answer

1 accepted

2 votes
Answer accepted
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 2, 2023

Hi @Danielle Gordon-Davids and welcome to the Community!

If you have already defined your hierarchy, then you should just use the parent link field to select the initiative as parent of an Epic.

When you pull your initiatives in the plan that also has your epics (probably as an additional issue source), then you can even drag your epics onto the desired parent initiative to create the link.

Hope this helps!

Danielle Gordon-Davids November 3, 2023

Hi @Walter Buggenhout , where do you find the parent link field?

Danielle Gordon-Davids November 3, 2023

Thanks, I found it!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events