We're building out a NextGen JIRA instance, using Epics and subtasks. I'd love to have the ability to show the subtasks due date in the parent ticket view.
Is this possible with NextGen?
Thanks in advance....
Hi @Dan Mallory
This is not yet possible in the new view (which Next-Gen utilises) - see this enhancement request to vote / watch its progression here: JRACLOUD-70206
It's still possible in Classic Projects though via Advanced Config - see this answer which has the instructions.
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If this is for Next-Gen, then it will display the due date by default if you're grouping by that statistic - to do this:
^ Using this method, the due date will appear on the card view for Subtasks, which will also appear on your board view.
If this is for Classic, you can change what is shown on the card layout via Board Settings:
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.