If we close a sprint and select that issues move to the next open sprint what happens to time spent?

Jules
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 13, 2024

We are using the sprints in jira cloud. We are unable to use versions due to having sprints that span multiple projects. 

When we come to close a sprint I am aware that we will be asked if we wish to move any incomplete tasks on to another open sprint. 

My question is what happens to the time tracking information so if ticket A is 50% complete and has 2h logged against it and is in sprint X when we close sprint X if the ticket moves to sprint Y will the 2h still be attributed to Sprint X or will the time also move to Sprint B 

Its important for resource tracking so we can identify what was worked on in which sprints when we create our sprint reports. 

Thanks in advance 

1 answer

0 votes
Chris Buzon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 15, 2024

Time spent is independent of sprints.  It will just carry over as part of the time spent on the ticket, not time against a sprint.