I have set up a kanban board with stories and tasks linked together. can a burndown chart be created

Peter_Green
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 1, 2019

I have set up stories as work elements to which Tasks are related representing portions of work required to complete the Story.  The tasks are assigned duration times to complete. Can a burndown chart be run in Jira to indicate progress?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 1, 2019

Yes, Jira Software has burndown charts.

When a story issue (with an estimate on it) goes into the last column of a scrum board, it is considered "done" and burndown happens then.

Note that your "linked tasks" are separate entities, your scrum board will need to include people moving those tasks to "done" as well.

Peter_Green
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 3, 2019

Thanks Nic. Appreciate your input.