How to update the remaining estimate in jira?

Siddik March 18, 2016
 

2 answers

1 accepted

2 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 18, 2016

Log some work and adjust it (you don't have to set an amount of work done if you take that route)

Siddik March 18, 2016

adjust meaning... do i have to set the remaining time back to the estimated effort.. that way the remaining estimate stays the same?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 18, 2016

It's up to your process what you do with the numbers.

Deleted user September 23, 2020

@Nic Brough -Adaptavist- may be you have some idea about if we can change the default option of the "Remaining Estimate" to set to (not globally but Project specific)  ? Can we do it somehow with Script Runner / Automation or is there any other Plugin known to you which could help ?

0 votes
stratejos [stratejos.ai] March 18, 2016

In terms of process, the most effective use we see of remaining estimate is to ensure it always reflects the time remaining to complete a task/issue. This means that either a project manager reminds you to update it or you update it because you realise something has changed. Sometimes you may realise on the spot that things have changed - e.g. you realise the task is harder than initially thought or you uncover new requirements for the task. Sometimes you realise the remaining estimate needs to be updated because you are logging your time and see that it isn't/won't be accurate.

With this in mind, in order to update the remaining estimate, here are some specific instructions when using JIRA. 

Option #1: Update Remaining Estimate when logging time

When ever you log time using the Log Work button then the remaining estimate can be updated. Ideally, you entered an Original Estimate when you created the issue/task.

Step 1: Enter an Original Estimate (and remaining if not done automatically) when you create a task

Step 2: Log Work

Go to the Log Work screen to log your time/work. This can be found on the issue itself.

logwork-1.png

 

Step 3: Update the Remaining Estimate for the task

After clicking Log Work you should see the Log Work screen popup like the one below. Enter the time you've spent and then choose how you want to update the remaining estimate. Using "Adjust Automatically", JIRA will take the current Remaining Estimate and reduce it by the Time Spent that you enter. 

logwork-2.png

 

Option #2: Update the Remaining Estimate only/independently

If for some reason you realise that the Remaining Estimate is going to be longer or shorter than currently set for a given task then you can update the Remaining Estimate by going to the task and clicking Edit. You should then see something like the screen below (after scrolling down on the Edit popup):

update-remaining.png

Deborah Intilla
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 20, 2020

Hey, 

Option 2 is exactly what I need, but how can we do this in the new view? 🙏 

Thanks!

Like # people like this
Sushmina Manandhar March 31, 2021

How can we do Option 2 in the new Jira view?

Suggest an answer

Log in or Sign up to answer