Hi. I am not a Jira Admin - just a Project Admin (and Project Lead) - and also new to Jira.
Our team works to two-week development sprints. Our sprint board contains the following columns: To Do, Analysis, Development, QA and Done. All issues are planned for a single sprint ahead of time, and at the end of the two weeks, all issues would hopefully have been moved to the "done" status and the sprint is closed.
However, just because we have finished our development, it does not necessarily mean our work has been released to a production environment. It could be another two, three or even more weeks until an issue is required to be pushed live. (We are responsible for promoting issues to production as well as developing them)
Our stake-holders now want to be able to see a list of all issues which have been completed as far as development is concerned, but not yet pushed to production. What is the best way to set this up? I thought about just adding another swimlane to our board - maybe something like "Development Complete" and place that just before the "Done" column. But if I did that, as each sprint closes, I would have to move un-released issues from the current sprint to the next - and maybe even to the one after that. This is messy, but would mess up our reporting.
Is there a better solution?
Thanks