Request your support how to create a field for Effort Variance (%) for Task and Sub-task. This is required for one of the project.
Value of the new field is based on the following calculation.
Effort variance = (Time spent - Original Estimate)/ Original estimate*100. Kindly revert for any clarifications.
Thanks and regards
Nirmalya
I strongly recommend Performance Objectives for Jira plugin to compute various KPIs.
There is a build-in work ratio field, but it doesn't consider subtasks. You can even use it in JQLs like workratio > 100 to find underestimated works. You may create a new custom field plugin by modifying its code.