How do you get the Pie Chart showing Parent and Child tasks status?

Danish Akhtar January 24, 2024

Pie chart -Jira.JPG

The Pie chart above is showing only 25 Total tasks. But they do not include the child tasks(sub-tasks). This does not represent the actual progress of the project. How can I include the child-tasks also?

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 24, 2024

Hello @Danish Akhtar 

Actually the counts do include subtasks.

However, the entire chart includes only the issues that display on the board, not all issues in the project. JWM will automatically hide issues that have been "done" for 14 days or longer, and those issues won't be included in the charts on the summary page.