I need to change the resolved date from one of my JIRA issues from 11/10/2023 to 10/20/2023, but it doesn't seem like I can do that.

I saw JIRA-cloud allows to update it, but I am wondering if JIRA-Server system allows that.

If any solutions to this issue are already brought up, please let me know!

Thank you!

1 answer

0 votes
Ste Wright
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 19, 2023

Hi @Caleb Park 

Not via the native UI, the Resolution Date sets to the date/time of resolution.

You'd need to do this via the database, a recommendation for this is made in this question - but I'd be very careful doing this.