Hello Team,
I have a requirement to write a JQL Query in the Automation Rule for Jira Service Mgmt.
I need to find all the requests which are approaching due dates for less than 3 days from the expected completion date.
for e.g if the completion date is 04/22/2022 so today is 04/19/2022 then the jql should return all such request information which are in progress.
Quick response is highly appreciated.
Community moderators have prevented the ability to post new answers.
This question came up a couple of times in the past, see this thread for some creative ideas:
For Service Desk marking issues as After Hours, I used the following:
createdDate >= startOfWeek(6d) AND createdDate <= startOfWeek(7d)
like this:

You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @iftekhar sayyed ,
unfortunately there's no a specific operator for this. you need to use startOfWeek()/endOfWeek() in your JQL in order to manually exclude specific weekend.
Hope this helps,
Fabio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Community moderators have prevented the ability to post new answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.