Hi,
We have setup a "Company-managed business" Project in Jira. It seems like it is not possible to change the parent issue for an existing issue in this setup. Could you please guide me how I can enable this feature so that we can, for example, move stories in between Epics?
In my screenshot, the issue is part of an epic but I cannot "move" the issue under a different epic (the option is missing):
Thank you for your help
Hello @Henrik Thiess
Welcome to the Atlassian community.
You will need to add the Epic Link field to the Screen for that issue type. Then you can edit that field to change the parent Epic for an issue.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You're welcome.
If you have been able to solve your problem with help from my answer, please consider clicking the Accept Answer button.
If you still are unable to solve the problem, please let us know.