Dependence line not showing for "has to be done after"

Jim Lindenthal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 6, 2024

I am trying to graphically show the dependency link line on the timeline view for two specific tasks.  When I add a link issue using "is blocked by" the line appears between the two tasks.  When I add a link issue using "has to be done after" the line does not appear.  I have illustrated this scenario in the attached view of my timeline.  We are using the JIRA Software Standard AdditionDependence.JPG

1 answer

1 vote
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 6, 2024

In the Timeline view in the Standard subscription only the "blocks" link is supported for indicating dependencies. Refer to

https://support.atlassian.com/jira-software-cloud/docs/manage-dependencies-between-epics-on-the-timeline/

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events